Behind the construction fencing at the southwest corner of South Beach Parkway and Jacksonville Drive, on city-owned land near Home Depot Plaza, Jacksonville Beach is building a passive park. The plans call for native vegetation, seating, informational signs and water stations, and the site is designed to tie into the city's Urban Trail work next to South Beach Park. That short list explains the park. It is built for people already walking or riding somewhere, and the corner gives them a place to stop.
Three Years From Open House to Clearing Crews
This park has been in the works longer than most people driving past would guess. The timeline, drawn from city documents and local coverage:
- August 23, 2023. The city held an open house on a proposed park on the west side of South Beach Parkway at Jacksonville Drive. Even then the plans listed native vegetation, seating, signage, water stations and a link to the urban trails project.
- FY2025–2029 capital plan. The city's Capital Improvement Program set aside $900,000 for the passive park. The CRA's FY2026 budget carries that $900,000 under Southend tax increment funds.
- FY2026 goals. The Community Redevelopment Agency's FY2026 business plan lists finishing construction of the park as a Southend District goal.
- June 2026. Construction began, with crews clearing invasive plants and overgrown vines while keeping significant trees, protected buffers and healthy native plantings.
- August 24, 2026. CRA staff told the board the existing vegetation was in worse shape than expected and announced new tree funding to replace it.
- Late September to early October 2026. This was the window the city gave in July for substantial completion, weather permitting.
The design changed very little between the 2023 open house and the 2026 construction fence. Seating, signs, water and a trail connection stayed the plan the whole way through, which shows what the city has wanted this corner to do.
A Park Planned Around Sitting
The best way to read the new park is next to the one already across the parkway. South Beach Park & Sunshine Playground, at Osceola Avenue and South Beach Parkway, is one of the most heavily equipped parks at the Beaches.
| South Beach Park & Sunshine Playground | New passive park at Jacksonville Drive | |
|---|---|---|
| Location | Osceola Avenue and South Beach Parkway | West side of South Beach Parkway at Jacksonville Drive |
| Sports | Multipurpose turf field, basketball court, two pickleball courts, convertible tennis court, three sand-volleyball courts | None listed in published plans |
| Play and movement | Children's playground, skatepark, fitness trail with exercise stations, seasonal splash pad | Planned tie-in to the Urban Trail project |
| Rest and comfort | Picnic shelters | Seating, water stations |
| Landscape | Maintained grounds and turf | Native vegetation and more than 100 new trees and native plantings |
| Information | n/a | Informational signage |
The two parks split the work between them. South Beach Park is where the Southend goes to play. The published plans for the new corner list shade, water and somewhere to sit, with no sports or play equipment among the features named. That only works because of what sits around it. The CRA's FY2026 plan also commits to ongoing upkeep at South Beach Park, including more ADA-compliant sidewalks and multi-use paths. The capital plan, meanwhile, budgets $1.5 million from FY2025 through FY2027 for Southend connectivity corridors. These are meant to support safe walking and biking between neighborhoods, parks, commercial areas and the beach, and to connect to the city-funded urban trails.
Put a playground-heavy park, a quiet planted corner and a budget for paths between them on the same stretch of South Beach Parkway, and you have a route with a busy end and a calm stop along it. The water stations make the most sense for someone who arrived on foot or by bike.
The Edge Is the Slowest Part to Grow
The biggest change since the clearing crews arrived concerns the park's edge. Once the underbrush came out, crews found that most of the vegetation could not work as a natural barrier for the homes around the property. CRA Coordinator Taylor Mobbs described what they found at the August 24 board meeting, as Beach Gazette reported:
"Once they got in there and started clearing out a lot of the underbrush, what we thought was a healthy barrier and buffer is not. There were a lot of invasive plants and a lot of dead plants."
Trevor Hughes, Jacksonville Beach's chief of parks development and maintenance, worked with the Jacksonville Tree Commission to fund a new landscape buffer. The commission, an advisory panel created in 2017 to grow the city's urban tree canopy, agreed to pay for more than 100 trees and native plantings. Any healthy existing trees stay.
The time frame Mobbs gave is the detail that sets this project apart. In the same Beach Gazette account, she described a plan for a buffer that "over the next five, 10, 15 years will actually grow into a buffer that is intentional and serves a purpose." Count forward from 2026 and the full screen around this corner arrives somewhere between the early 2030s and the 2040s. CRA member Thad Moseley pointed to the stopgap, noting that fast-growing, dense native shrubs fill in quickly while the trees take about a decade to mature.
So the park has two finish dates. The benches, signs and water stations can be finished this season. The planted edge will keep changing for years, and a visitor in 2030 will see a fuller corner than a visitor this fall.
The city also tied the change to the homes nearby. Mobbs said door hangers with the updated landscaping plans would go to the 14 adjacent residents before more clearing began, and that the change did not alter the project timeline, as Beaches Beacon reported.
What $900,000 Means in the Southend
A dollar figure needs something to measure against, and the CRA's own books provide it. The Southend Redevelopment District generated $3,431,342 in tax increment revenue in FY2025, compared with $10,853,077 for the Downtown District. The $900,000 budgeted for the passive park equals roughly a quarter of one year of Southend increment. The $1.5 million connectivity line comes to a little under half.
Those revenues come from property taxes collected inside the district and held in a separate trust fund, so the money spent on this corner was raised in the Southend. With about a third of downtown's yearly increment to work with, the Southend has chosen to spend it on shade, native planting and paths, and a park planned around seating and native trees fits that choice.
The Name Comes Last
The park is still unnamed. City officials have said a community survey will choose the name. At the July 15 CRA meeting, staff said they planned to propose 10 to 12 name options for that survey.
The naming survey is the next public step, and it is the easiest way for people on the Southend to have a say in a corner they will pass for years. The City of Jacksonville Beach posts updates through its news and calendar pages, and CRA meetings are where staff have given progress reports all year.
When the fencing comes down, the corner of South Beach Parkway and Jacksonville Drive will have benches, water, signs and young trees, a short walk from the courts, skatepark and splash pad at South Beach Park.
If you live near South Beach Parkway and have questions about how projects like this one shape the blocks around them, the advisors at Christie's International Real Estate First Coast follow Southend changes closely. Get in touch and we will gladly share what we are seeing.